Message from the Management[041181]

Share underwriting agreement between LC Energy Ltd. and Citizen Investment Trust (CIT) on 04/11/2081 Today

...

February 16, 2025
Read More

Message from Management(200881)

It is to inform you all that All EM components and HM pipes are reached at site. 

Installation of EM components in...

December 6, 2024
Read More

Message from Management (020881)

All Electromechanical components from Flovel (India) arrived Nepal and are in provress to tranfer at site. Transfering of EM components will ...

November 17, 2024
Read More

Message from the Management [240581]

Construction of three major structures ( Headworks structure, Surge tank and Powerhouse) are completed. Almost 84% of the construction works ...

September 9, 2024
Read More

Message from the Management [14052081]

The construction of Surge tank structure has been completed Today

...

August 30, 2024
Read More

Message from the Management [051280]

Engineers from Consultant have plan to visit Flovel factory (India) on 06/12/2080 (Tuesday) for inspection of the Pelton Turbine for Lower Ch...

March 18, 2024
Read More

Message from the Management [281080]

The Consultant Engineer with NEA team are in India for inspection of Transformer from           ...

February 11, 2024
Read More

Message from the Management[121080]

The pipe supplier Deep Seals India Ltd. has plan to dispatch first lot of pipes by 1st week of February/2024.

...

January 28, 2024
Read More

Message from the Management [041080]

The Client with consultant engineer are planning to visit for pipe inspection at Deep seal India Ltd. (Pipe supplier) in India on 05/10/80.&l...

January 18, 2024
Read More

Message from Management [260880]

The Consultant Engineer with NEA team are planning to travel Bengaluru (India) for inspection of Generator on 19/Dec/2023. And will be return...

December 14, 2023
Read More

Message from Management [05082080]

The civil work at site resumed from 05/08/2080 (Tuesday) after Tihar/Chhat holidays

...

November 21, 2023
Read More

Message from the Management

It is to notify/request you all (respected shareholders) to inject the additional Promoter share, if interested. We are at the final stage to...

November 8, 2023
Read More

Message from Management [070923]

Bank LC has been opened for Deep Seals (India) Limited (HM supplier) for the manufacturing of spiral pipes for the Project. Tentative date to...

September 7, 2023
Read More

News from Management [110580]

Tri-party meeting with Prabhu bank and Maha Laxmi Bikash Bank held on 11/05/2080 at Prabhu Bank headoffice to add Mahalaxmi Bank as consortiu...

August 28, 2023
Read More

News from Management[280480]

All works (Civil / Hydromechanical / Electromechanical / Transmission Line / Connection hub) are in progress. The work progress at Site are l...

August 13, 2023
Read More

General massage [070480]

The Management would like to request all our respected shareholders to add the equity share as possible as you can from your side. &...

July 23, 2023
Read More

EM works

Bank LC for Electromechanical Supplier (Flovel) has been opened. And fabrication of electromechanical equipment by Flovel is in process.

July 2, 2023
Read More

General Message 150380

All major structures (Headpond tank, overflow spillway, connecting canal) at Headworks area have been completed. Works at powerhouse area are...

June 30, 2023
Read More

News from Management [28-02-80]

Civil amd HM-II works are in active progress. Progress @ EM and HM works are little bit delayed due to delay on loan disbursement from the Ba...

June 11, 2023
Read More

News from management

Civil works at both Headworks and Powerhouse area are in active progress, HM phase-II work is also in progress. We have plan to complete all ...

May 7, 2023
Read More

HM Contractor (Phase-II) works

HM phase-II contractor has started their works and manufacturing of bends, embedded parts, gates are in progress

...

April 30, 2023
Read More

Disbursement of Loan

Bank has just started disburse BG loan, which makes easy to move Project forward for some extent.

...

April 26, 2023
Read More

Sub station works

Bank has issued Bank LC today [19-Apr-23] for importing electrical components from India for connection bay at Tumlingtar sub-station. Fabric...

April 20, 2023
Read More

Sub-station works

Construction of connection hub at Tumlingtar sub-station began

...

April 18, 2023
Read More

Site works

Civil works at Headworks site are in active progress and EM initial earthmat design has been approved and manufacturing of earthmat materials...

April 16, 2023
Read More

Message from Management

This is to inform all shareholders that each shareholder's personal message box will be updated every Friday 10:00 AM to 11:00 AM and work pr...

April 16, 2023