
Message from the Management[041181]
Share underwriting agreement between LC Energy Ltd. and Citizen Investment Trust (CIT) on 04/11/2081 Today
...
Share underwriting agreement between LC Energy Ltd. and Citizen Investment Trust (CIT) on 04/11/2081 Today
...
It is to inform you all that All EM components and HM pipes are reached at site.
Installation of EM components in...
All Electromechanical components from Flovel (India) arrived Nepal and are in provress to tranfer at site. Transfering of EM components will ...
Construction of three major structures ( Headworks structure, Surge tank and Powerhouse) are completed. Almost 84% of the construction works ...
The construction of Surge tank structure has been completed Today
...
Engineers from Consultant have plan to visit Flovel factory (India) on 06/12/2080 (Tuesday) for inspection of the Pelton Turbine for Lower Ch...
The Consultant Engineer with NEA team are in India for inspection of Transformer from ...
The pipe supplier Deep Seals India Ltd. has plan to dispatch first lot of pipes by 1st week of February/2024.
...
The Client with consultant engineer are planning to visit for pipe inspection at Deep seal India Ltd. (Pipe supplier) in India on 05/10/80.&l...
The Consultant Engineer with NEA team are planning to travel Bengaluru (India) for inspection of Generator on 19/Dec/2023. And will be return...
The civil work at site resumed from 05/08/2080 (Tuesday) after Tihar/Chhat holidays
...
It is to notify/request you all (respected shareholders) to inject the additional Promoter share, if interested. We are at the final stage to...
Bank LC has been opened for Deep Seals (India) Limited (HM supplier) for the manufacturing of spiral pipes for the Project. Tentative date to...
Tri-party meeting with Prabhu bank and Maha Laxmi Bikash Bank held on 11/05/2080 at Prabhu Bank headoffice to add Mahalaxmi Bank as consortiu...
All works (Civil / Hydromechanical / Electromechanical / Transmission Line / Connection hub) are in progress. The work progress at Site are l...
The Management would like to request all our respected shareholders to add the equity share as possible as you can from your side. &...
All major structures (Headpond tank, overflow spillway, connecting canal) at Headworks area have been completed. Works at powerhouse area are...
Civil amd HM-II works are in active progress. Progress @ EM and HM works are little bit delayed due to delay on loan disbursement from the Ba...
Civil works at both Headworks and Powerhouse area are in active progress, HM phase-II work is also in progress. We have plan to complete all ...
HM phase-II contractor has started their works and manufacturing of bends, embedded parts, gates are in progress
...
Bank has just started disburse BG loan, which makes easy to move Project forward for some extent.
...
Bank has issued Bank LC today [19-Apr-23] for importing electrical components from India for connection bay at Tumlingtar sub-station. Fabric...
Construction of connection hub at Tumlingtar sub-station began
...
Civil works at Headworks site are in active progress and EM initial earthmat design has been approved and manufacturing of earthmat materials...
This is to inform all shareholders that each shareholder's personal message box will be updated every Friday 10:00 AM to 11:00 AM and work pr...